In the Fall of 2022, voters in the South Colonie Central School District approved two capital project propositions that together will result in $120 million in improvements across the district.
Since voter approval, Board of Education members and district leadership have been working collaboratively to engage stakeholders on the first stage designs. The design work for Stage I of the project has been submitted to the New York State Education Department (NYSED) for approval with construction plans set to begin on South Colonie campuses as early as Spring 2024.
“We are excited to share that during our Board meeting on Tuesday, Oct. 17, our architects provided a comprehensive update, including a draft milestone timeline for Next Generation Colonie Stage I,” said Dr. David Perry, superintendent of schools. “This significant step forward is a testament to our commitment to improving our facilities for the benefit of our students and the entire community.”
In addition to breaking ground on a slew of athletic upgrades including a new synthetic turf and sports complex, Stage I of Next Generation Colonie also includes classroom renovations at Colonie Central High School and Shaker Road Elementary. This stage also involves revitalization of the auditorium at Lisha Kill Middle School and other notable improvements, including the redesign of the Shaker Road Bus Loop and a new front facade at Lisha Kill Middle School.
Full presentation can be found here.

Here is a summary of the draft timeline for the various components of Stage I, organized by date and location:
Colonie Central High School
Lisha Kill
Sand Creek
Forest Park
Roessleville
Shaker Road
Transportation
Colonie Central High School
Scheduled to begin April ‘24
-
- New Synthetic Turf Multi-Purpose Field
- New Home Side Bleachers w/ dual purpose press box
- New Concession Pavilion w/ toilet facilities and grand entrance
- New Lighting on main field and replacement lamps on soccer field
- New discus area, shot putt areas, long jump areas and
Scheduled to begin May ‘24
New Integrated FA/PA System
Scheduled to begin June ‘24
-
- New entry floor and floor finish in MUG corridor to ‘G’ Wing
- Renovated and enlarged athletic trainer suite & new gender-neutral bathroom(s)
- Renovated basement team / locker rooms, Pit locker rooms
- Renovation of wing B Classrooms and creation of AIS rooms
- Replacement of building envelope with curtain wall system & new UV’s in classrooms with futureproofing for possible AC.
- Renovations to library support spaces
- Replacement of select exterior doors and improvements to door access control
- Mechanical upgrades including add alternates for AC in classrooms
- Roof reconstruction at the MUG, Pit Gym and Math Wing
Scheduled to begin June ‘25
-
- Renovation of ‘F’ wing classrooms
- ‘F’ wing windows/Façade work
Lisha Kill
Scheduled to begin June ‘25
-
- Resurface Tennis Courts and New Backboards
- Replacement of building envelope with curtain wall system & new UV’s in classrooms with futureproofing for AC.
- Renovation of Auditorium to include stage rigging, lighting, sound, acoustic control, house finishes
Sand Creek
Scheduled to begin May ‘24
New Integrated FA/PA System
Scheduled to begin June ‘24
- Roof Replacement
- Stormwater Detention System Replacement
Forest Park
Scheduled to begin June ‘24
-
- Reconstruction of sidewalks and ADA entrances
- Select exterior door replacement
Scheduled to begin June ‘25
Roof Replacement at Gym
Roessleville
Scheduled to begin June ‘24
-
- Replacement of exterior storefront/Window system
- Select exterior door replacement
Scheduled to begin June ‘25
Roof Replacement at Gym
Shaker Road

Scheduled to begin June ‘24
-
- Reconstruction of bus loop, staff and visitor parking, hardcourt play area, emergency access road and sidewalks
- Removal of Old lift pumps and sanitary / storm tanks
Scheduled to begin July ‘24
Removal of wooden play structures and reinstatement of grass
Scheduled to begin April ‘25
- Renovation of six classrooms into model 21st century learning environments
- Renovation to main office and nurse suite
Scheduled to begin June ‘25
-
- Replacement of exterior storefront system
- Select exterior door replacement
- Roof replacement at Gym
Transportation Facility
Scheduled to begin Summer/Fall ‘25
-
- Electric Infrastructure Work
- Gas Line Re-Routing
- Demolition of Buildings B, C, and D and Site Stabilization